Strained power grid halts Bethesda hospital plans

The Defense Department must spend $37 million to expand the Bethesda military hospital\'s overloaded power grid, after a substation at the National Institutes o...

Hundreds of millions of dollars in construction planned for the Bethesda Walter Reed National Military Medical Center is now on hold, The Washington Examiner reports.

The Defense Department must first spend another $37 million to expand the center’s overloaded power grid, after a substation at the National Institutes of Health reached capacity.

That means it won’t be able to power the improvements — totalling about $781 million — needed to meet BRAC requirements for revamping the site’s medical services and accommodating the hundreds of new patients and workers.

Congress is waiting for a definitive answer from the Defense Department on whether the electricity issues at the substation could lead to brownouts or blackouts at the hospital.

Meanwhile, officials said building a better grid could take as long as two to three years, The Examiner reports.

This story is part of Federal News Radio’s daily DoD Report. For more defense news, click here.

Copyright © 2024 Federal News Network. All rights reserved. This website is not intended for users located within the European Economic Area.

    Biden Trump

    After delay, Trump signs agreement with Biden White House to begin formal transition handoff

    Read more
    (Getty Images/iStockphoto/Kiyoshi Tanno)Signboard of United States Department of Veterans Affairs

    VA updates FY 2025 health care budget shortfall to $6.6B, nearly half its previous estimate

    Read more