Richard Lieberman, a consultant and retired attorney, offers advice to contractors about how to ensure they are protected when they win a request for quote.
While the use of a request for quotation (RFQ) for a procurement may not be a true “no-win” situation, it may come close to that for a government contractor. That is particularly true when the contractor misses the delivery date, as in TTF, LLC, ASBCA No. 58495. The supplier has made what is called “the RFQ mistake.”
Follow the scenario below, which is abbreviated, but is essentially what TTF faced:
Agency issues an RFQ for 37 aircraft fuselage fairings.
TTF submits a responsive quote to the agency, which negotiates the price down slightly.
Agency issues a unilateral purchase order (PO). The PO states “TTF is not required to sign the PO in order to indicate acceptance.” TTF does not sign it.
Delivery date specified in the PO is 180 days after award.
TTF cannot comply with the delivery date, but sends a letter requesting a 120-day extension due to “vendor delays.” The contracting officer doesn’t respond to the letter.
181 days elapse — no delivery
The contracting officer sends TTF a letter stating that its failure to deliver means the PO has lapsed, and she is canceling the PO. No termination action is necessary — TTF is out of luck.
What’s going on here? The Federal Acquisition Regulation (FAR) is driving the result. FAR 2.101 recognizes two types of offers: (1) responses to invitations for bids in sealed bidding are offers called bids or sealed bids; (2) responses to requests for proposals in negotiated procurement are offers called proposals. However, responses to requests for quotations are not offers but are quotations or quotes.
When the government issues a purchase order in response to a quotation that order is merely an offer by the Government— a contract is established only when the supplier accepts the offer. The supplier may indicate its acceptance of the order in writing, or the supplier may indicate acceptance by furnishing the supplies or services ordered or by proceeding with the work to the point where substantial performance has occurred. Unless the contractor has signed and accepted the purchase order, the government at any time before acceptance occurs, withdraw, amend or cancel its offer.
So when TTF got its order (the Purchase Order), it had two ways to accept it:
By signing the PO and returning it to the agency as an “acceptance.”
By not signing, but by proceeding with the work (and delivering the supplies).Do you see the mistake? The agency sent the purchase order with the statement that “the contractor is not required to sign the PO in order to indicate acceptance,” and TTF didn’t sign it. (Acceptance will only occur later, if the contractor delivers the goods). If the contractor had signed it, there would have been a complete contract at the outset. Of course, if the contractor had accepted it, the government still could have terminated the contract for default, but there would have been a contract in place. In TTF (and many earlier cases like this), the board held that there was no contract, and the PO had lapsed by its own terms (the non-delivery of the goods). The contractor got no relief at all.
Tips: Don’t make the RFQ mistake. If you receive a purchase order, sign it and accept it and send your signature back to the agency. You will then have a contract. Then you must perform, or have valid reasons for non-performance. By accepting the government’s order in writing, you prevent the agency from withdrawing, amending or canceling its offer at any time before acceptance occurs later — upon delivery of the goods or services.
Richard Lieberman is a consultant and retired attorney. This article does not provide legal advice as to any particular transaction.
The RFQ mistake
Richard Lieberman, a consultant and retired attorney, offers advice to contractors about how to ensure they are protected when they win a request for quote.
While the use of a request for quotation (RFQ) for a procurement may not be a true “no-win” situation, it may come close to that for a government contractor. That is particularly true when the contractor misses the delivery date, as in TTF, LLC, ASBCA No. 58495. The supplier has made what is called “the RFQ mistake.”
Follow the scenario below, which is abbreviated, but is essentially what TTF faced:
What’s going on here? The Federal Acquisition Regulation (FAR) is driving the result. FAR 2.101 recognizes two types of offers: (1) responses to invitations for bids in sealed bidding are offers called bids or sealed bids; (2) responses to requests for proposals in negotiated procurement are offers called proposals. However, responses to requests for quotations are not offers but are quotations or quotes.
When the government issues a purchase order in response to a quotation that order is merely an offer by the Government— a contract is established only when the supplier accepts the offer. The supplier may indicate its acceptance of the order in writing, or the supplier may indicate acceptance by furnishing the supplies or services ordered or by proceeding with the work to the point where substantial performance has occurred. Unless the contractor has signed and accepted the purchase order, the government at any time before acceptance occurs, withdraw, amend or cancel its offer.
Join WTOP Nov. 21 for an exclusive conversation with congressional and health care industry leaders about what is on the nation's health care policy agenda right now. Register today!
So when TTF got its order (the Purchase Order), it had two ways to accept it:
Tips: Don’t make the RFQ mistake. If you receive a purchase order, sign it and accept it and send your signature back to the agency. You will then have a contract. Then you must perform, or have valid reasons for non-performance. By accepting the government’s order in writing, you prevent the agency from withdrawing, amending or canceling its offer at any time before acceptance occurs later — upon delivery of the goods or services.
Richard Lieberman is a consultant and retired attorney. This article does not provide legal advice as to any particular transaction.
Copyright © 2024 Federal News Network. All rights reserved. This website is not intended for users located within the European Economic Area.
Related Stories
Rethinking continuous risk metrics to fortify federal cybersecurity
AI emerging as a not-so-secret business development weapon for government contractors
Correction to connection: Making federal performance review season less spooky